UPHJS2014
Pre. Exam

83. Which section of Urban Planning and Development Act, 1973 mandates that after declaration of any area as development area under section 3 of the Act no development of land shall be undertaken or carried out unless permission for such development has been obtained in writing from the Vice Chairman.
(A) Section 12
(B) Section 14
(C) Section 41
(D) Section 15

Answer and Notes Answer is B

UPHJS2009
Pre. Exam

40. The authority competent to grant permission for development of land in a development area under U.P. Urban Planning and Development Act, 1973 is-
(A) Development Authority
(B) Chairman of the Development Authority
(C) Vice-Chairman of the Development Authority
(D) State Government

Answer and Notes Answer is C

UPHJS2018-II
Pre. Exam

30. Completion Certificate, under the Uttar Pradesh Urban Planning and Development Act, 1973, if not granted or refused after service of statutory notice, is deemed to be granted after expiry of :
(a) Sixty Days (b) Six Months
(c) Three Months (d) One Month

Answer and Notes Answer is C



Explanation: Section 15-A of Uttar Pradesh Urban Planning and Development, 1973 lays down provision for Completion Certificate. It provides that if completion certificate is not granted and refusal to grant it is not intimated within three months after receipt of the notice of completion, it shall be deemed that the Completion certificate has been granted by the Authority .